Natural candidate
Standardised workloads
Supported Linux or Windows VMs, known dependencies, reproducible networking and measurable availability objectives.
VMware Exit
Decide on evidence: inventory, compatibility, POC, target architecture, migration waves and documented rollback.
Authorisation criteria
These criteria come before the schedule and any cutover promise. Each gate produces verifiable evidence. If a criterion fails, the wave does not start: the scenario is corrected, postponed or excluded.
Inventory, criticality, dependencies, change windows and application owners are validated.
The POC measures performance, network, storage, backup, HA and operations on representative workloads.
A first non-critical wave validates the procedure, application checks and rollback.
Each batch has a runbook, owner, stop criteria and proof of restorable backup.
Decommissioning after stabilisation, documentation, knowledge transfer and business approval.
Decommissioning rule
The VMware source remains available until the target is stable, restores are validated, technical and application owners approve, runbooks are handed over and the business owner gives formal acceptance.
A VMware Exit is more than a hypervisor swap. It must make the economic case, technical constraints and the team's ability to operate the target explicit.
Not always. A credible VMware Exit starts by segmenting the estate: what can move, what requires a POC and what should temporarily remain on VMware or use another target.
Natural candidate
Supported Linux or Windows VMs, known dependencies, reproducible networking and measurable availability objectives.
Prove in a POC
Low-latency databases, appliances, application-aware backup, HA, replication or vSAN/NSX dependencies require representative tests.
Decision required
Certification, an unsupported appliance or a contract requiring vSphere may justify a hybrid path or a documented exception.
Precise mapping: VM list, CPU/RAM/storage consumption, network dependencies, critical applications identified.
Design of the target architecture based on production constraints and continuity objectives: network segmentation and resilience, high availability strategy, storage architecture and sizing adapted to real workloads — not a generic template.
VM prioritization: non-critical first, critical last with parallel VMware production maintained.
Exhaustive application tests, SLA validation, controlled switchover, VMware decommissioning after stabilization.
You leave with operational material for architecture, operations, security, procurement and application owners — not a generic recommendation.
It depends on the scope, production constraints, application dependencies and available migration windows. Some migrations are done in progressive waves over several months to minimize operational risk.
Each wave has a defined rollback path, tested where the workload allows it. The VMware source is retired only after technical, application and business validation.
Not necessarily. Proxmox VE runs on standard x86 hardware. We assess whether existing hardware is compatible and sufficient.
That's our goal. We provide runbooks, operational documentation and train your system administrators.
No. vSAN and NSX capabilities must be separated by use case: distributed storage, micro-segmentation, routing, automation and observability. The POC validates useful equivalents and documents functions that require another component or a hybrid path.
The target includes a tested backup strategy, RPO/RTO objectives, recovery scenarios and an explicit support model. These are GO/NO-GO criteria, not tasks postponed until after cutover.
Compare costs, review our production experience and validate your architecture on representative workloads.
Share your estate, constraints and timeline so we can frame the next useful decision.
Assess my VMware Exit plan